Bunker Lake Blvd and Puma Street Improvements (Updated November 21, 2018) IP 18-05

  • Bunker Lake Boulevard, east of Puma Street, and Puma Street, north of Bunker Lake Boulevard, will receive pavement, storm sewer, and trail improvements in 2018. 
  • On Wednesday, August 22, 2018, Douglas-Kerr Underground, LLC. began storm sewer construction along Bunker Lake Boulevard, east of Puma Street. The Contractor anticipates storm sewer construction will take 1 week to complete, weather depending. During this construction, Bunker Lake Boulevard will be closed to traffic from Puma Street to Jackal Street. The Contractor will begin installation of storm sewer along Puma Street after the Bunker Lake Boulevard storm sewer has been constructed, during which time Bunker Lake Boulevard will be re-opened to traffic and Puma Street will be closed to traffic from Bunker Lake Boulevard to Alpine Drive.
     
    Storm sewer construction is complete. Week of Sept 10th, the Contractor is placing class 5 aggregate base. Week of Sept 17th, 2018 Contractor will be placing concrete curb and gutter, followed by bituminous pavement, then boulevard restoration. After the storm sewer is constructed, temporary delays may be experienced, and access may be restricted at times due to construction. At least one access will be maintained to all properties during construction.
  • Week of October 1 - 5, 2018, the Contractor is placing the base course of bituminous pavement.  As always, their work is weather dependent.
  • Week of October 8, 2018 the Contractor started work on the trail improvements.
  • Construction is substantially complete November 19, 2018.

  • Final completion will occur in 2019.