Stanhope Terrace St Reconstruction IP 18-00 (Updated June 22, 2018)

  • Approximately 0.5 miles of streets will be reconstructed using a full-depth reclamation (FDR) process.
  • Streets will primarily remain open to traffic during construction.
  • Construction update letters will be mailed to affected property owners during construction. 
  • Week of June 4 - June 8, 2018, Weather this week hampered North Valley, Inc.'s progress slightly, and we wanted to give residents time to repair/relocate their irrigation systems.
  • Week of June 11 - June 15, 2018, North Valley, Inc. plans to have backfill behind curbs complete and restore the boulevards with turf. Four inches (4")  of topsoil will be placed over all disturbed areas before sod is installed. 
  • Week of June 18 - June 22, 2018 North Valley, Inc. plans to reinstall mailboxes June 18 and 19. The wear course (upper lift) of pavement, is scheduled to be completed by the end of the week (June 22 or early following week). As always, their work is weather dependent.
  • Construction is substantially complete June 21, 2018